Stage payments against physical milestones
Work here is funded as it proceeds; material purchase follows payment. The correct structure ties each payment to a milestone that a person standing on the beach can verify as done or not done — keel and stem erected, garboard fitted, turn of the bilge planked, sheer strake closed, framing complete, decking laid, caulking and primer complete, launch. Percentage-complete milestones are unverifiable and should not appear.
Two protections are worth insisting on. First, payment released on inspection rather than on invoice date. Second, a retention held until after handover, so that defects found at survey have a remedy. How wooden vessel contracts are structured covers the mechanism in detail, including why a late payment costs more time than the length of the delay.